The first of a new phase of St Modwen’s Longbridge development the Waters Building is a combined Headquarters and production facility totalling 45,000sqft.
Cavish were initially contracted to undertake the full earthworks and groundworks package including the following elements:
Whilst undertaking the works Cavish were approached due to our previous experience with FM2 power floated floors to undertake this element of the works which included an intricate joint layout and varying depths/thickenings due to final manufacturing machine placement.
All works were completed working together with Speller Metcalfe’s site team in just 38 weeks.